Data Management Capabilities > Managing Projects > Classic Plans > Classic Plan Objects > Classic Plan Object Information Pages
  
Classic Plan Object Information Pages
A plan object information page is a collection point for information related to the plan object. The information page of a particular plan object (plan, activity, summary activity, milestone, or subproject) is accessed by clicking the information icon in the plan table, or selecting View Information from the Actions drop-down menu on the plan table.
From the information page, you can perform actions on a plan object, as well as view the object attributes and any related information.
For an overview of information page functionality, see About Information Pages and Customizing Information Pages.
Actions
Information pages contain a list of applicable actions in a menu in the upper left corner of the page. See Actions for a list of common actions available in Windchill. The availability of these actions depends on the status of the plan object, as well as your access to it. For more information about status indicators, see Status Indicators.
The following actions may be of particular interest for this object.
Action
Description
New Deliverable
Opens the New Deliverable window so that you can create a new deliverable associated with the plan object. You can also create a new deliverable from Project > Tasks or Program > Tasks in the Navigation pane.
Add Deliverables
Opens the Add Deliverables window which enables you to search for existing deliverables to associate with the plan object.
Move To
Moves the plan object to the specified position within the plan.
Insert Activity Below
Creates a new activity in the plan that is directly connected to the existing plan object.
Insert Milestone Below
Creates a new milestone in the plan that is directly connected to the existing plan object.
Insert Summary Below
Creates a new summary activity in the plan that is directly connected to the existing plan object.
Insert Sub Project/Program Below
Creates a new subproject in the plan that is directly connected to the existing plan object.
Tabs
The following tabs are viewable on the plan object information page. You can customize the tabs that appear on each object information page to display the information most useful to you. For more information, see Customizing Information Page Tabs
* 
Administrators may have modified the tabs that are viewable to you.
The Details tab provides specific information about plan object attributes. The Attributes table contains the detailed information for any particular plan object. See Attributes for a list of common attributes available in Windchill. The following attributes may be of particular interest for plan objects:
Attribute
Description
Name
The unique identifier for the object. An icon preceding the name identifies the type of the plan object.
Description
A brief description of the plan object. This field is not used for subprojects.
ID
A unique identifier assigned to the plan object by the system.
Owner
The team member who has been assigned to the plan object.
State
The state of the plan object, such as Defined, Running, Completed, Canceled, and Suspended.
Due Date
The date by which the plan object is to be completed.
Predecessors
Predecessor plan objects define constraint relationships for the current plan object. For example, if Activity A is named as a predecessor to Activity B, then Activity B cannot be started until Activity A has been completed.
Followers
Follower plan objects are those that cannot be started until the current plan object is completed.
Child
The actual name of the project or program related as a subproject. Because a subproject may have been defined without any particular project or program being associated, this field may be blank.
* 
This field is only applicable to subprojects.
Description
A brief description of any child projects or programs.
* 
This field is only applicable to subprojects.
Done
The percentage of the plan object work that has been completed.
Actual Effort
The amount of time (in hours) that was actually dedicated to the completion of the plan object. This field is not applicable to milestones.
Estimated Effort
The amount of dedicated time (in hours) expected to be necessary in order to complete the plan object. This field is not applicable to milestones.
Status
The status of the plan object, either Green, Yellow, or Red. Green indicates no problems. Yellow indicates caution. Red indicates an alert of high risk. The unavailable icon indicates that the status is unavailable.
Status Description
A brief description of the reasons for the status designation.
Risk
The level of risk that the plan object will not be completed by the specified due date.
Risk Description
A brief description of the reasons for the risk designation.
Estimated Start
The date on which work on the plan object was to have begun.
Start Date
The start date assigned to the plan object during its creation.
Estimated Duration
The number of days expected for the plan object work to be completed.
Actual Duration
The number of days passed between the start date and the completion date (a plan object is considered completed when it reaches 100% done).
Estimated Finish
The date on which the plan object was expected to be completed.
Finish Date
The date on which the plan object was completed. This date is calculated according to when the plan object reaches 100% done.
Actual Cost
The actual cost of the work involved in completing the plan object. This field is not applicable to milestones.
Estimated Cost
The estimated cost of the work involved in completing the plan object. This field is not applicable to milestones.
Budget
The budget amount allotted to the project or program. This field only appears for subprojects.