Windchill Operation Attribute
|
SAP Operation Attribute
|
Operation Label
|
Activity
|
Description
|
Description
|
Base Unit of Measure
|
Operation Measure Unit
|
Distribution Target
|
Plant information in the distribution target if there is no work center associated to operation. If a work center is associated to the operation then plant information is taken from the work center's attribute.
|
Set up Time
|
Setup time and Unit of Measure for Setup time.
|
Processing Time
|
Machine time and Unit of Measure for Machine time
|
Labor Time
|
Labor time and Unit of Measure for Labor time
|
Waiting Time
|
Wait Time & Wait Time Unit
|
Queue Time
|
Queue Time and Queue Time Unit
|
Move Time
|
Move Time and Move Unit
|
Quantity
|
Base Quantity
|
ERP Validation Code
|
Control key
|
Work Center Link
|
Work Center
|
|
Setup time, Processing time and Labor time are dependent on the work center selection. By default these times are mapped based on the following work center: |
|
If the work center is different from the above settings (for example, Work center category, Standard value key, Usage) then it is possible that the default mapping will cause data corruption. You must make the necessary customizations detailed in the Windchill Enterprise Systems Integration Customizer's Guide - SAP. (refer to the section Customization for Operation Timings).
|
Operation Related Attribute in Windchill MPMLink
|
SAP Operation Attribute Value
|
Work center number from the operation work center association
|
Work center
|
Plant from the operation to work center association link
|
Plant
|
Distribution target
|
Plant information in the distribution target, if there is no work center associated to the operation. If a work center is associated to the operation, the plant information is fetched from the work center's attribute.
|
ECN number
|
Change No
|
Sequence Line number from Sequence for Sequence operation
|
Sequence number. For an operation in a standard sequence it is "000000"
|
Process Plan number
|
Group number
|
Operation label of the Parent operation in case of sub operation
|
SubActivity
|
SAP Operation Attribute
|
Default Value
|
Control Key
|
If ERP Validation Code = K1 then PI01
If ERP Validation Code = K2 then PI02
If ERP Validation Code = K3 then PI03
If ERP Validation Code = ”” then PP01
|
Denominator
|
1
|
Nominator
|
1
|