When publishing a Process Plan with an operation, there must be a work center, with a department, assigned to the operation. The work center should also have time values attributed to it, to allow for the creation of activities. If there are no time values attributed to the work center then no activities are created. To schedule resources the Unit of Measure (UOM) for the resource should be set to Hour (HR). In addition, the resource group to which the processing resources and work centers belong should also be used.
|
Process Plan Attribute
|
Oracle Applications Routing Attribute
|
Revision
|
Revision of the Routing
|
Distribution Target
|
Organization
|
Parts
|
Item number
|
Operations
|
Operations
|
Resources
|
Resources
|