User Help > Grouping Units of Work in Change Packages > Moving Change Package Entries > To move change package entries in the Web interface
 
To move change package entries in the Web interface
1. From a Project or Member History view, click the change package ID. The Change Package view displays.
2. Click the Entries tab. The Entries panel displays.
3. Select the change package entries you want to move.
4. Select Actions > Move Change Package Entry. The Move Change Package Entry dialog box displays.
5. From the Target Change Package list, select the change package you want to move the entries to. The change packages are listed with the C.P. ID and the summary, for example, 10:1 help dialog broken.
6. If you want to create a new change package for the entries, click Create.
7. When you are finished, click OK. The Confirm Move Change Package dialog box displays.
8. To move the entry, click Yes. Repeat for additional entries. The change package entries are moved to the selected change package.