To move change package entries in the GUI
1. From the Entries panel on the Change Package view, select the change package entries you want to move.
2. Select Change Package > Entry > Move. The Move Change Package Entry Settings dialog box displays.
3. From the Target Change Package list, select the change package you want to move the entries to. The change packages are listed with the C.P. ID and the summary.
4. If you want to create a new change package for the entries, click Create.
5. If you are a change package administrator, the Show all open Change Packages option is available. Select the option to make change packages that you did not create available in the Target Change Package list.
6. When you are finished, click OK. The Confirm Move Change Package dialog box displays.
7. To move each entry presented, click Yes. To move all entries without viewing individual prompts, click Yes to All. The change package entries are moved to the selected change package.
* 
On the Change Package view, you can move change package entries by dragging them from one Change Package view to another.
You can also move change package entries using the Working File Changes view. Select the change package entries you want to move. Select a different change package from the Change Package list and click Move to Change Package.