Electrical Design > Adding Wires > To Change the Wire Path
  
To Change the Wire Path
1. Click Insert > Jog. You are prompted to select the wire, highway, or rail at the position where you want to add a jog.
2. Select the position for the new jog. Diagram assumes that you are starting to sketch from the end of the original segment that is closer to the position used to select the segment.
You can create one or more jogs by selecting successive points. A jog is added at a position wherever you click. If you place additional jogs, it is like resketching that one piece of wire, with the end of the sketched section connected with a rubberbanding segment to the other end of the originally selected piece.
3. Middle-click to stop placing the jog.
 
* To delete a jog, use Edit > Remove > Jogs.